Reduce Shotcrete Cycle Times by 35%

Author: Harry

Aug. 19, 2024

Reduce Shotcrete Cycle Times by 35%

Reduce Shotcrete Cycle Times by 35%

Mesh and bolt reinforcement systems have long been the standard reinforcement systems in underground construction, however it is not conducive to high productivity and continuous development cycles. Fiber reinforced shotcrete and bolting as a primary support system has eliminated these hurdles.

TRM are exported all over the world and different industries with quality first. Our belief is to provide our customers with more and better high value-added products. Let's create a better future together.

Synthetic fiber reinforced shotcrete (MSFRS) was first used on a mass scale in underground mining and today it&#;s standard practice in both mining and civil tunnelling ground support across Europe, America and many other regions.

MSFRS offers numerous benefits over the traditional mesh and bolt support system;

  • Increased performance.
  • Durability is increased by eliminating corrosion.
  • Site safety is increased as workers reduce and eliminate time under unreinforced ground.
  • The application process can be automated.
  • Speed of development is substantially increased.
  • Concrete cover is not required.
  • Significant capital cost reduction.

Table 1: Published by G. Methvin (), &#;Shotcrete: More Engineering Developments&#;, shows a direct time comparison for synthetic fiber reinforced shotcrete vs mesh and bolt reinforcement systems.

Mining Cycle with Mesh Bore face 2.0 hours Charge & fire 1.5 hours Clear smoke 0.5 hours Hose & scale 0.5 hours Bog 2.0 hours Bolt & mesh
(4 sheets mesh & 15 bolts) 4.5 hours Face clean up 4.5 hours Total (average time) 11.5 hours Mining Cycle with Shotcrete Bore face 2.0 hours Charge & fire 1.5 hours Clear smoke 0.5 hours Hose & scale 0.5 hours Bog 4 buckets 0.5 hours Shotcrete to face 0.5 hours Bog remainder 1.5 hours Bolt to face 0.5 hours Total (average time) 7.5 hours

 

It is clear that synthetic fiber reinforced shotcrete has the ability to greatly reduce cycle times, reducing direct project costs and providing a faster return on investment. Proof of this has been documented across numerous infrastructure project, such as the Mt Ovit Tunnel project in Turkey.

If you are looking for more details, kindly visit Mesh Bolt.

When combined with increased performance, site safety and reduced maintenance the arguments in favour of this support system become overwhelming, and further explains why it has experienced such a rapid increase in global use over the past decade.

You can read the full paper by following the link below.

 

 

 

Want more information on Friction Bolt? Feel free to contact us.

38

0

Comments

0/2000

All Comments (0)

Guest Posts

If you are interested in sending in a Guest Blogger Submission,welcome to write for us!

Your Name (required)

Your Email (required)

Subject

Your Message (required)

0/2000